In the fall of 2015, our Board began extensive assessment of the needs for our pool renovation. After thorough review of the scope and bids, Premier Pool Renovations of Plymouth Meeting, PA was selected as contractor this month.

Major demolition work began on March 11th.

Our anticipated renovation timeline is 60-75 days dependent on weather conditions this spring, but we plan to be open for Memorial Day weekend.